Concurrent Delay and Float Ownership: Who Gets the Time
When two delays overlap — one the owner's, one the contractor's — entitlement to time and money turns on concurrency rules and on a single contract question: who owns the float.
Key takeaways
- Concurrent delay occurs when an owner-caused and a contractor-caused delay overlap on the critical path during the same period.
- The general rule: concurrent delay usually entitles the contractor to a time extension but not to delay damages for the overlapping period.
- "Who owns the float" determines whether non-critical slack belongs to the owner, the contractor, or the project — and who can consume it.
- Many contracts state that float is a shared project resource available to whoever needs it first, which favors the party that uses it sooner.
- Accurate, contemporaneous critical-path schedules are the evidence that wins or loses concurrency disputes.
- Watch clauses that make any delay 'the contractor's' regardless of cause, or that strip float from the contractor automatically.
What concurrency does to entitlement
Delays rarely happen one at a time. When an owner-caused delay (a late design release, an unapproved submittal) overlaps on the critical path with a contractor-caused delay (a manpower shortfall, a subcontractor's slip) during the same window, the delays are concurrent. The widely applied rule is that concurrent delay entitles the contractor to a time extension — because part of the delay was the owner's — but denies the contractor delay damages for the concurrent period, because the contractor would have been delayed anyway. The owner likewise cannot collect liquidated damages for a period in which it contributed to the delay.
The result is a kind of standoff: time is extended, but neither side collects money for the overlap. Which delays were truly concurrent, and which sat on the critical path, becomes the entire fight.
Float: the most valuable thing nobody prices
Float is the slack on non-critical activities — the days a task can slip without delaying the project. Whoever "owns" the float controls a buffer that can absorb delay without consequence. Contracts allocate float three ways: to the owner, to the contractor, or to the project as a shared resource. The shared-resource model — float belongs to the project and is available on a first-come, first-served basis — is common and quietly favors whichever party consumes it first, often the owner through change-order sequencing.
A contractor that builds float into its schedule and then loses it to an owner-driven resequencing has effectively given away time it earned. That is why float ownership is a term to read, not assume.
Why the schedule is the evidence
Concurrency and float disputes are won with contemporaneous critical-path-method schedules, regularly updated, that show what was actually on the critical path when. A reconstructed, after-the-fact schedule built for litigation carries far less weight than baseline and monthly updates created in the ordinary course. Contracts increasingly require CPM scheduling, timely updates, and notice of delay events precisely because that record decides these claims.
Subcontractors should keep their own records even when the GC controls the master schedule, because a sub's entitlement can be lost in the gap between what happened and what the official schedule documented.
At contract review
Find the float-ownership provision and understand who controls the slack. Flag clauses that assign all delay to the contractor regardless of cause, that bar time extensions for concurrent owner delay, or that let the owner consume float without compensation. Confirm the notice and scheduling requirements you must meet to preserve a delay claim.
These provisions are easy to miss in dense general conditions, and they decide real money. A first-pass review should surface the float and concurrency language so your team negotiates it before the schedule — and the dispute — is underway.
This article is general information about construction contracting and law, not legal advice. Construction law varies significantly by jurisdiction and project. Consult qualified counsel about your specific contract and circumstances.
Put this into practice on your own contracts.
Redline Construction Solutions applies your firm's non-negotiables and jurisdiction-aware standards to mark up a contract automatically — and returns it ready for your team to review.
See how it works